Dear Homeowners,

Evans Construction is almost back on schedule.  They will finish the chip seal portion of the project tomorrow.  A crew will start picking up the excess chips tomorrow and work through the weekend.  There will be no traffic delay with the sweeper.

Fog Seal is still schedule for August 1st and 2nd.  Plan on a 30 minute delay once the fog seal is placed over the chips.

As noted on the “What to Expect – Do’s and Don’ts”, there will be an overspray of oil that may end up on your property.  Continue to water and mow your lawn as the oil will not kill your grass.  It will take a couple weeks, but your lawn will go back to normal.